Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Facilities topic

No spam. Unsubscribe anytime.

District reports bathroom renovation progress, multipurpose field delays and plan for new digital PA/clock system

Le Roy Central School District Board of Education · May 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent Merritt Holly updated the Board on Jr./Sr. High bathroom renovations (tile installation, subcontractor repairs), weather‑delayed multipurpose field work pending NYS DEC wetland determination, architectural interviews for building condition survey work, and a planned move to a digital clock/PA system.

Superintendent Merritt Holly updated the Board on multiple facilities items: Jr./Sr. High bathroom renovations are underway with tile installed and subcontractor repairs in progress pending final walkthroughs; multipurpose field work has encountered weather delays and the district is awaiting a wetland determination from NYS Department of Environmental Conservation. The district interviewed six architectural/engineering firms for the five‑year building condition survey and will contract Young & Wright Architects for survey work while retaining Clark Patterson for capital projects.

Mr. Holly also reported the high school PA system and clocks are problematic and that the district intends to move to a digital clock/PA system rather than temporary repairs. The minutes note the district will obtain additional warranties on work and tiles and continue coordination with contractors.