Superintendent outlines capital-project phases for bus garage, maintenance building

Tioga Central School District Board of Education · March 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Administration told the board that the final phase of a capital project will focus on the wash bay and fire-alarm system in the bus garage and that phase I will address a new bus garage and maintenance building, with initial conversations planned for elementary-school phase II.

Superintendent Joshua Roe told the board that a construction meeting would finalize details on the final phase of the district's last capital project, specifically focusing on the wash bay and fire-alarm system in the bus garage. "At tomorrow’s construction meeting we will finalize details on the final phase of the last capital project that will focus on the wash bay and fire alarm system in the bus garage," Roe said.

Roe said staff will also finalize details for Phase I of a new bus garage and maintenance building and begin initial conversations on a Phase II project at the elementary school. The minutes do not include cost estimates, timelines, or contractor names; board members will receive project-level budget and scheduling information at future meetings once the administration completes design and procurement steps.