Commission recommends setback variance for Canadochly Road addition, 4–0

Lower Windsor Township Planning Commission · February 27, 2025

Summary

The Planning Commission recommended the Zoning Hearing Board grant a variance to reduce a side setback from 10 feet to 5 feet for an addition at 1036 Canadochly Road; applicants said the permit had not been issued and no construction begun, and the motion passed unanimously.

Owner Amy Gundrum, represented by partner Jeremy Nolt, asked the commission to recommend a variance reducing the required residential side setback from 10 feet to 5 feet for a proposed building addition. The applicants said they had submitted a permit application that was approved except for stormwater management, and that when they located the property corner pins they found the addition would be five feet from the property line rather than the 17 feet they had initially expected. The permit has not been issued and no work has commenced.

Dr. Hollis Bedell moved to recommend that the Zoning Hearing Board grant the variance for this instance only; Marzena Wolnikowski seconded and the commission voted 4–0 to recommend approval. Jeremy Nolt summarized site context for the commission, noting the neighboring lot is approximately 9 acres and the nearest neighboring house is roughly 210 feet away and separated by woods.

“When we found the property corner pins, the addition would only be five (5) feet off the property line,” Jeremy Nolt said during the presentation. The commission specified the recommendation applies to this addition only and forwarded the recommendation to the Zoning Hearing Board.

Provenance: topicintro SEG 005, topfinish SEG 006.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source