Construction update: interior work advancing but tile and locker shipments delayed by tariffs
Summary
District construction lead said interior work is nearing completion, a June 5 punch‑list is planned, but some bathroom tile and lockers remain at the dock because of tariff‑related delivery issues that could affect exterior work timing.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
District construction updates noted that interior finishes are progressing — carpet and ceiling tiles are in place in many rooms — and the district set a June 5 punch‑list date for interior inspections. "We did set a June 5 date for a punch list, punch list for interior inspections," the Director said.
The Director also reported supply delays: bathroom tile and some lockers are sitting at the dock because of tariffs, which may require substitutions or color changes and could delay exterior boulevard and sidewalk work. "We might have to look at doing some different tile or different color," the Director said, adding that change orders so far total roughly $40,000–$50,000 (about 1% of the project).