Board approves capital-project change orders, including a $223,365 roof insulation and other repairs
Summary
The board approved emergency and additional capital project change orders that include multiple line items such as $223,365 for additional wet insulation and roof replacement and other site, masonry and roofing repairs; motions carried by voice vote.
Get email alerts on the Capital Project topic
No spam. Unsubscribe anytime.
The Eden Central School District board approved a set of emergency and additional change orders for ongoing capital projects, agreeing to line-item costs read aloud by the clerk.
The clerk listed emergency items including Slate Ridge repairs ($8,270), refinished stage chairs ($6,936), mezzanine ceiling patch ($2,835), curb access panels ($4,078) and an "additional replacement of wet insulation and roof" totaling $223,365, plus other masonry and gutter repairs. The board then approved a second set of change orders that included a $85,973 HDPE replacement, additional granite curbing and other site-work costs. Each motion was seconded and carried by voice vote.
Why it matters: the approved change orders allocate district funds for construction and urgent repairs tied to the ongoing capital project and will affect project budgets and schedules. The clerk also moved to approve an amended negative-declaration environmental resolution related to the 2024 capital-improvement project.
Next steps: project managers will implement the approved repairs and update schedules; the business office will reflect the changes in capital accounting.