Presenter: EMS building about 80% complete; breakers must be replaced before occupancy
Summary
A presenter told the Marlboro County Council the new EMS building at the hospital is roughly 80% complete but external disconnect breakers are seized by oxidation and must be replaced before the building can be used; the presenter also updated the council on septic work, loading-dock and mezzanine demolition and said paving is moving along.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
A presenter addressed the Marlboro County Council with a facilities update, saying the new EMS building at the hospital location is about 80% complete but that work has been held up by seized exterior electrical disconnect breakers that must be replaced for safety. "We can't put anyone and move forward unless we have a safe electrical system at that location," the presenter said.
The presenter described other active work on the site, including septic system installation, loading-dock repairs, doors and lighting, and removal of an old steel mezzanine to clear space: "the old steel mezzanine that was tons and tons of old steel has all been taken down so that a delta project on the building part is moving along really good," the presenter said. A staff member also noted that "The paving project is moving along." No estimated completion date or final cost was provided in the available transcript segments.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.