Navarro ISD bond projects remain on schedule; chiller replacement complete

Navarro Independent School District Board of Trustees · March 23, 2026

Summary

AG/CM Melisa Nu'u told the board bond projects are on schedule: shot-put/discus equipment installed, Tennis Court 4 concrete poured, baseball/softball press boxes set, chiller replacement completed, and RFP bid date extended to March 31 to add canopy scope.

AG/CM Project Manager Melisa Nu'u updated the board on 2021 and 2024 bond project progress, saying all bond-related projects remain on schedule and listing completed and in-progress work across athletic and campus sites. Work items noted included installation of field-event equipment, concrete poured for Tennis Court 4, delivery and placement of baseball and softball press boxes, visitors’ amenities and elevator tower work, fieldhouse interior rough-ins and masonry, scoreboard structure erection, and completion and commissioning of the chiller replacement project.

Nu'u also reported that the bid date for the elementary and intermediate refresh RFP was extended to March 31 to accommodate Addendum 3, which adds scope for canopies at the rear of the elementary, painted playground games and a basketball-court canopy. Fire-line inspections at Navarro South Elementary passed with the City Fire Marshal, and coordination is ongoing for a west-side water-line tie-in.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source