County engineer reports paving progress; board approves $48,187.54 final payment
Summary
County Engineer updated the board on County Road 18 paving, detours and milling; commissioners approved a final payment of $48,187.54 to the contractor for two SAP projects.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
County Engineer (presented as Todd Grafton) updated commissioners on paving and detour work, equipment operations and remaining punch‑list items for multiple road projects.
Grafton described work on County Road 18 and related detours, noting confusion when drivers follow phone apps rather than official detour signage. "Google Maps takes you through the shortest route, which is right down our County Road 10," he said, adding that state crews and contractors are coordinating to reopen parts of the route and finish paving before winter.
Grafton also requested approval of a final payment for two SAP projects (listed as SAP609039 and SAP0756880). The board approved the final payment to the contractor in the amount of $48,187.54 after a motion and voice vote. Commissioners and staff also discussed gravel crushing plans for the next fiscal budget and timing for remaining construction tasks.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.