Rec center project back on a revised schedule; small net change orders reported
Summary
The city's recreation and aquatic center remains on track for turnover in the third week of July next year after contractor schedule adjustments; recent change orders netted a small increase and the project-management committee retains change-authority.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Bob Beanstrom, who updated the council on construction of the indoor recreation and aquatic center, said exterior work is largely complete and interior trades are focusing on mechanical and electrical systems. He reported the competition pool is "pretty well constructed" and work is beginning on the recreation pool; the track upper-level slab is poured but the floor still needs finishing.
Beanstrom said the contractor Stahl has pulled schedule back and the city is now "anticipating the turnover will be that 3rd week of July" next year. He summarized two recent change orders: one increased the contract by about $18–19,000 and another reduced it by about $12,000, leaving a net change of roughly $6–7,000 for the month. Beanstrom also noted the project-management committee's delegated change-order authority was increased from $200,000 to $300,000 previously, and the committee had about $84,000 of that delegated authority remaining.
Asked by councilors, Beanstrom said change orders are slowing as the project moves indoors and are mostly coordination or owner-request items rather than major design modifications. "The changes have kinda settled in where we're probably gonna have 1 or 2 a month for the next while," he said. Staff invited questions but reported that, at present, the project is not in danger of exceeding the committee-authorized change threshold.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.