Public Works: Wastewater plant basins complete; clarifiers due within weeks

Jacinto City Council · May 28, 2026

Summary

Public Works Director Thomas Rogers reported contractors have completed both contact basins at the Wastewater Treatment Plant and that clarifiers are expected to be installed within the next couple of weeks, which will complete this portion of the project.

Public Works Director Thomas Rogers told the council that contractors are progressing well at the Wastewater Treatment Plant and that both contact basins are complete.

"The clarifiers are expected to be installed within the next couple of weeks, which will complete this portion of the project," Rogers said. He reported the department continues normal maintenance of water and wastewater systems and that several employees have attended training this week.

Rogers added the department is preparing equipment for hurricane season and noted a staff member, Alex, passed his exam and received a license as a Mosquito Operator, adding operational resilience for seasonal spraying.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source