Pampa ISD updates progress on PHS CTE/Fine Arts addition, HVAC and elevator work
Summary
Director of Operations reported construction progress across district projects: PHS CTE/Fine Arts addition on schedule, Admin HVAC prep started, elevator modernization and PHS roof nearing completion, and Pampa Elementary pad work completed.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Troy McClendon, the district's Director of Operations, reported progress on multiple capital projects. He said Scottco has begun work preparing the administration HVAC for installation planned in late July, the PHS roof is expected to finish in early to mid-July, and elevator modernization at PHS should be ready by the next school year. On the new PHS CTE/Fine Arts addition, McClendon said it "should be dried in within 6-8 weeks" and "will have air conditioning in 12 weeks."
At Pampa Elementary, pad work was completed and the slab pour and steel delivery are scheduled for the summer with concrete parking lots planned rather than asphalt because of longevity concerns. McClendon also said the district hopes to issue bidding documents next month for a district-wide energy management system and expects a guaranteed maximum price (GMP) to be ready by the June Board meeting.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.