McCamey ISD hears progress report on High School Phase 2 construction
Summary
Gallagher Construction told the McCamey ISD board that exterior auditorium and band hall concrete pavers are complete, parking lot striping is in progress, AV work is ongoing and auditorium carpet installation is scheduled to begin soon.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Matt Miller of Gallagher Construction updated the McCamey ISD Board on High School Phase 2 construction at the Dec. 17 meeting. He reported that exterior auditorium and band hall concrete paver installations are complete, parking lot striping is in progress, auditorium audio and visual installations are underway and carpet installation is scheduled to begin soon.
The update provided progress milestones but did not include a revised completion date or contract dollar amounts in the minutes. Board members were present for the briefing and no formal action (award or change order) was recorded in the minutes in connection with the construction update.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.