Board selects Design Group Inc. for South High School Phase 7 design; project budget $3.2 million
Summary
The board voted to recommend Design Group Incorporated (architects/planners) for design services on the South High School Phase 7 final project, a $3.2 million package; the firm will return with a negotiated contract.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The board approved recommending Design Group Incorporated Architects and Planners to provide design services for South High School Phase 7, a project administration described as a $3,200,000 package covering construction and associated "soft" costs.
"This is a $3,200,000 project," the presenter said, explaining the RFQ process produced 11 responses, a shortlist of three, and interviews that included South High School representation. Administration said the selected firm will negotiate a contract and return to the board for approval of the contract terms.
Presenters detailed that the phase will complete unfinished areas from earlier packages — locker rooms, a receiving area, restrooms and improved wayfinding — and estimated a schedule to finish construction work by the end of the next calendar year. Board members praised the functional improvements, including a proposed receiving area and family restrooms to support athletics and theater uses.
If the board’s recommendation stands, the next step is contract negotiation and a return to the board for final contract approval.