Headworks construction underway; mechanical screen expected in March 2026
Summary
Council heard that headworks concrete work is complete, tie-ins and electrical are ongoing, and the mechanical screen has been ordered with arrival expected March 2026; council members were offered a site visit.
Get email alerts on the Sewer Improvements topic
No spam. Unsubscribe anytime.
City Engineer Garry Montgomery reported the headworks sewer-improvement project is under construction. "All concrete has been poured, and work is ongoing on tie-ins, electrical, and the water system. The screen has been ordered and is expected to arrive in March 2026," Montgomery said, and he offered a site visit for council members to review progress.
Montgomery added that the plan is to finalize tie-ins for use with a manual screen initially and commence full operation when the mechanical screen is installed. He also said the final portion of the sewer project grant for manhole rehabilitations is being finalized and will likely go out for bids by the end of January.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.