Council tables awarding of Control Building contract after bids exceed budget
Summary
Bids for Contract 2 (Control Building at wastewater plant) came in over budget, prompting the council to table awarding the contract for further research; the motion to table carried unanimously Sept. 16.
Get email alerts on the Public Contracts topic
No spam. Unsubscribe anytime.
The Brundidge City Council voted Sept. 16 to table awarding Contract 2 for the Control Building at the wastewater plant after bids exceeded the project's budget.
Councilmember Hall moved to table the award until further research could be completed; Councilmember Gaynor seconded and the motion carried with all voting yea. The minutes record the reason for tabling as bids coming in over budget but do not include the bid amounts or an estimated revised budget.