Summary
Engineer Nathan Feist presented bonding and Bollig's project plan and introduced Task Order #8 (funding application/administration: $5,000 + 5% of funds secured) and Task Order #9 (well/wellhouse design: $230,000) for council consideration.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Nathan Feist, the city's engineering representative, briefed the council on bonding options and Bollig's plan for current and upcoming projects and introduced two task orders for council review. Task Order #8 covers funding application and administration at $5,000 plus 5% of any funding secured; Task Order #9 is for well and wellhouse design priced at $230,000.
Council did not take immediate final action on the task orders during the June 10 meeting but scheduled the items for focused discussion at a special meeting on June 22, 2026. The presentation framed the financial scope council must consider if proceeding with well infrastructure work.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.