Buna ISD reports progress on cosmetology lab, freezer construction and electrical work
Summary
Maintenance and operations staff updated trustees on cosmetology lab completion steps, a new elementary walk-in freezer slab, and an electrical service reroute to address a damaged weatherhead.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Maintenance Director Joe Menard and other operations staff told the board July 13 that the cosmetology lab workstations are painted and chairs have arrived; granite counters were scheduled for installation on 6/30 per the maintenance report and wash bowls remain to be installed. The slab for a new elementary walk-in freezer has been poured and freezer installation will follow.
Menard also reported that electrical service for the administration office is being rerouted underground to remove a weatherhead that has been causing roof damage, with coordination planned with the contractor to minimize disruption. Routine maintenance on ice machines and HVAC systems was reported as complete; other projects such as installing plates on walk gates and finishing the junior high electrical work were in progress.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.