Council approves $62,000 change-order settlement for delayed contractor work
Summary
Council approved a consent-agenda change order resolving a contractor delay tied to a construction contract. Staff said the contractor and Clive negotiated a liquidated-damages offset of $62,000 and the council approved the contract amendment by a 5–0 vote.
Get email alerts on the Contracts topic
No spam. Unsubscribe anytime.
Council voted to approve a negotiated change order resolving delay claims on a public works contract. Councilmember Klein and staff explained the city and the contractor jointly negotiated a liquidated-damages arrangement to address project delays; the change order incorporates a $62,000 offset to the contract.
Councilmember Weaver moved to pull item 14 from consent for discussion; after staff explained the negotiated settlement, the council moved and seconded approval and the clerk recorded a 5–0 vote in favor. Staff said the parties had agreed to the figure and only formal amendment of the contract remained to complete the process.
No additional conditions or amendments were recorded in the meeting; staff indicated they would proceed with formal contract amendment paperwork following council approval.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.