Council hears Phase 2 timeline for ELGT Connector; construction expected June–July
Summary
Borough Manager Michelle Evans reported a staff timeline for Phase 2 of the ELGT Connector project: bid package by end of April, bid award in May, construction starting in June and completion by July.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Borough Manager Michelle Evans told Council that Phase 2 of the ELGT Connector Project has an estimated schedule: the bid package should be ready by the end of April, the bid award is expected in May, with construction starting in June and finishing by July. The minutes list those target milestones without additional budget or contractor names.
Council received the schedule as informational. No motion, vote, or contract award was recorded in the April 6 minutes; the item remains a project update in staff reporting pending formal bidding and award actions.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.