Chief: new fire station site work underway; completion hoped by Labor Day 2027

Pacin City Council · August 19, 2026

Summary

Chief Scott reported that grading and fill are underway at the new fire station site, geotechnical work and a pre‑construction meeting are next steps, and the team hopes for completion around Labor Day 2027 (timeline described as approximate).

Chief Scott updated council on progress at the new fire station and adjacent park. He said the city has a permit for grubbing and ground work, fill is being brought in to raise the site elevation (to reduce flooding risk), geotechnical work (geopiers) will start the following week, and a pre‑construction meeting is being scheduled.

When asked about completion timing, Chief Scott said the contractor's schedule suggests about a one‑year timeline once work begins and stated, "I'm hoping it'll be done by Labor Day of next year," while cautioning the date was not guaranteed. Council and staff discussed a future groundbreaking and open house once site work is complete.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source