Board tables May Road sanitary sewer Change Order #4 for contractor clarification

Manchester Township Board of Supervisors · July 8, 2025

Summary

Engineer B.J. Treglia reported quantity discrepancies on the 2024 sanitary sewer work; the board voted to table Change Order #4 while staff and contractor resolve outstanding items.

Engineer B.J. Treglia updated the board on completion of 2024 sanitary sewer projects and ongoing communication with the contractor concerning quantity discrepancies tied to the May Road project. Supervisor Harry M. Long, Jr. moved to table action on Change Order #4; Supervisor David J. Chiaverini seconded the motion.

The board tabled the change order to a future meeting to allow additional review and resolution with the contractor. The motion carried unanimously (Ayes‑4, Nays‑0).

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source