WUHS renovation remains on schedule and budget; district expands sprinkler scope

Waterford Union High School Board of Education · June 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Administrators reported the renovation is on schedule and on budget, with abatement complete in the art area, HVAC and plumbing progress, a new water heater forthcoming, and cost savings allowing expansion of the fire sprinkler scope; a Village easement is being negotiated for the loading dock.

Superintendent Francois told the board June 15 that the Waterford Union High School construction project remains "on schedule and on budget." He highlighted completed abatement in the art area, progress on HVAC and plumbing in Area A, and the planned installation of a new water heater.

Francois said cost savings allowed the district to expand the fire sprinkler system to the entire school and reported a "street-vacate" issue concerning the loading dock is being resolved with the Village via a potential easement; the Village will also repave Field Drive this summer. Board members were invited to a walkthrough of D Wing and a video update of renovations was scheduled for June 16.