Commissioners approve $370,000 amendment for South Wellfield water project

Board of Greene County Commissioners · August 6, 2026

Summary

The Greene County Board approved Amendment No. 11 to the Barge Design Solutions agreement, adding $370,000 and extending the contract to Dec. 31, 2027 to support South Wellfield connection and well rehabilitation work for the Sanitary Engineering Department.

The Greene County Board of Commissioners on Aug. 6 approved Amendment No. 11 to the Barge Design Solutions, Inc. agreement to provide as-needed design and program management support for the Sanitary Engineering Department. The amendment extends the contract through Dec. 31, 2027 and adds $370,000 for the South Wellfield Connection and Well Rehabilitation project.

Commissioner Sarah J. Mays moved for approval of Resolution 26-8-6-4 and Commissioner Richard D. Gould seconded; the roll-call vote was Aye from Commissioners Tom Koogler, Sarah J. Mays and Richard D. Gould. The amendment is intended to fund design and program management work needed to install, upgrade and maintain water distribution components related to the South Wellfield project.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source