Planning commission: data centers can fit within township's 'high‑tech' use class

Upper Mount Bethel Township Planning Commission · February 19, 2025

Summary

Township zoning official told the Planning Commission that while 'Data Centers' are not explicitly named in Use Class 8, Use Class 8A (New Industrial Parks) permits high‑tech industries; the commission concluded a data center could be considered a permitted high‑tech use.

Commissioner Teel asked Township Zoning/Building Officer Tina Serfass whether data centers are a permitted use under the township zoning ordinance. Serfass said Use Class 8, as written, does not specifically call out "Data Centers," but Use Class 8A for new industrial parks lists research facilities, laboratories, high‑tech industries and technical centers that support these activities.

The commission recorded a determination that a "high‑tech industry could be a Data Center, a permitted use." That conclusion frames how future data center proposals will be evaluated under the current zoning text; the minutes do not record any formal zoning amendment or text change at this meeting, only an interpretive determination by staff and commissioners.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source