Banks SD 13 begins schematic design for high school; demolition, construction dates set
Summary
Banks SD 13 project team presented the start of schematic design, said demolition is planned this winter with construction of the high-school addition targeted for May 2026–August 2027 and occupancy aimed for Sept. 1, 2027.
Get email alerts on the Project Schedule topic
No spam. Unsubscribe anytime.
Banks SD 13 project staff told the board they are starting the schematic-design phase for the high-school project and will provide periodic updates on budget and schedule. Project timelines presented include demolition of affected buildings roughly December through March and construction of the high-school addition from May 2026 through August 2027, with target occupancy on Sept. 1, 2027.
Presenter John (project team) described staged work to expedite early site utilities and grading, saying the team will "break out some early work so we can get started on things ahead of the entire design being complete." He also said demolition and permit sequencing require coordination with Washington County and may involve a county hearing as part of the land-use process. The board asked for updates at key milestones; PNC will provide cost checks at the end of schematic design and later at design-development and 50% construction-document milestones.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.