Engineer reports punch‑list progress, paving scheduled at Fugo Tract
Summary
Entech Engineering reported contractors are addressing punch‑list items for the 2022 I & I Phase 4 sewer improvements and paving is scheduled this week at the Fugo Tract; a substantially complete letter will be issued for the 56‑62 Seventh Ave development.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Engineer Matt Boggs of Entech Engineering presented the Engineer's Report to the authority on March 25, 2025 and summarized work on several development and sewer projects. He told the board the contractor for the 2022 I & I Phase 4 Sewer Improvements project is addressing punch‑list items this week and that close‑out documents will be provided after the work is finished. Mr. Boggs also reported paving is scheduled for this week at the Fugo Tract Development and that only manhole adjustments remain before project completion.
Mr. Boggs said a substantially complete letter will be issued for the 56‑62 Seventh Ave Development and that the punch list has been provided to the contractor. He stated there was no update for the Castle Cove project and that construction at the Bronson Circle Development is anticipated to be scheduled for the summer.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.