Window replacements and exterior‑panel fix keep renovation on track before winter

HOUSTON PUBLIC SCHOOL DISTRICT · August 24, 2026

Summary

Staff reported new windows will be installed later this week, a revised exterior panel mounting method (clips plus LATICRETE adhesive) will keep the project on schedule despite a six‑week panel delay, and field/grading and gutter work will proceed in the coming weeks.

Staff updated the board on ongoing renovation and field work, saying crews completed tear‑out and board‑up of stairwell windows and that replacement windows will be installed later in the week.

"The new windows will be installed on Thursday and Friday of this week," the staff member said. Staff described a delay with an exterior panel adhesive system and said the contractor will use a mechanical clip system plus the LATICRETE adhesive to keep the project on the anticipated timeline; that approach is used elsewhere and both the district contact and builder were comfortable with it. Work on outfield drain tile, repurposing limestone material and finishing the concession building were scheduled to follow the panel and window work so the project should be completed before winter.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source