Public Works reports successful water testing, sewer flushing and storm‑sewer installs

Township of Reserve Board of Commissioners · October 1, 2025

Summary

Public Works reported that weekly September water testing for chlorine and bacteria returned satisfactory results, the crew completed quarterly meter reads, responded to 23 One Calls and installed 50 linear feet of 12" storm sewer line.

Public Works Chair Ed Vincent told the Board that for September staff performed weekly water testing for chlorine and bacteria and "all results were good." He also reported completion of quarterly water meter readings for the third quarter and continued locating customer curb boxes.

Vincent provided operational metrics: Public Works responded to 23 One Calls, installed 50 linear feet of new 12‑inch storm sewer line, replaced catch basins at Edison and Volta Streets, adjusted catch basins on Fleiner Street, assisted a CCTV camera crew locating manholes, attended a Public Works training day, and performed shop maintenance and repairs.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source