Council hears plan and phasing for Spaghetti Flats colonia engineering task order
Summary
Council considered a task order for engineering services on the Spaghetti Flats colonia improvement project. Staff described phased work beginning on North Lane and an anticipated bidding timeline with construction likely next spring/summer.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Council reviewed a task order for engineering, design and surveying services for the Spaghetti Flats colonia improvement project (CIF698). A presenter described the work as covering design and construction-phase engineering and said the contract would cover the full time the firm works on Spaghetti Flats.
The presenter said the project likely will be bid out in a couple months and estimated the work would not finish before March or April of the following year, adding that the project will be phased starting at the north side to avoid designing work in areas likely to be bought out. The presenter said pre-construction safety meetings with the contractor will take place to protect workers and the public. Councilors asked about easements, possible costs for acquiring them and whether storm-drain installation could increase project cost; staff said easement acquisition and unknown drainage work create uncertainty and could increase the final project expense.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.