Worcester supervisors approve $817,368.90 pay estimate for 2025 road program

Worcester Township Board of Supervisors · November 24, 2025

Summary

The board approved Pay Estimate No. 2 to Heidelberg Materials Northeast LLC for $817,368.90 after CKS Engineers confirmed the bulk of paving work is complete; remaining items include line striping and a 5% retainage. The payment covers work on multiple neighborhood roads as part of the 2025 program.

The Worcester Township Board of Supervisors approved Pay Estimate No. 2 for $817,368.90 to Heidelberg Materials Northeast LLC for the 2025 road paving program.

Michelle Fountain of CKS Engineers told the board the bid package and work have been reviewed and ‘‘most of the work is done except for the line striping’’; she recommended payment of $817,368.90, noting a 5% retainage will be held until final completion. Fountain said the estimate includes work on Crestline Drive, Hillside Circle, Longmeadow Road, Quail Run and other roads, and that the first estimate previously approved covered $119,197 of earlier work.

Public works and CKS inspected the completed paving and recommended moving forward with the second payment. A supervisor moved, seconded and the board approved the payment by voice vote. The manager and the engineer said a small final payment will follow after striping and completion of remaining punch‑list items.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source