Supervisor updates show progress on Mill Creek master plan and flood‑plain work

Town of Richmond Town Board · August 26, 2025

Summary

Supervisor Daryl Marshall reported completion of Mill Creek Master Plan Phase 1 and channel cleaning for Phase 2, that Phase 3 planning is funded and being developed by MRB, that NRCS planning funding has been restored, and that FEMA is following up on flood‑plain map concerns after Hurricane Agnus.

Supervisor Daryl Marshall used his report to provide several infrastructure and planning updates. He told the board that Phase 1 of the Mill Creek/Honeoye Outlet Master Plan is complete and Phase 2 channel cleaning has been done. Phase 3 is in planning: the town received a grant to develop the plan and The MRB Group has been retained to work on that phase.

Marshall also reported that Natural Resources Conservation Service (NRCS) planning is underway and that funding for that work has been restored. He said the town is participating in Honeoye Creek flood‑plain mitigation discussions tied to a Great Lakes watershed study and that FEMA is following through on concerns about flood‑rate impacts from Hurricane Agnus. No formal vote was required on those planning updates during the meeting.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source