County IT presented a plan to bring servers back on premise ahead of the Google enterprise agreement to avoid an expected $230,000 licensing bill and to renegotiate or end a roughly $48,000-a-month Google subscription; commissioners gave informal approval to proceed to the Q2 budget review for asset reappropriation.
Get email alerts on the It Infrastructure topic
No spam. Unsubscribe anytime.
Arapahoe County staff told commissioners they want to move county servers out of Google Cloud now rather than in 2027 to avoid sharply higher Microsoft licensing costs. Bridal Austin, the systems presenter, said the county can use fixed assets already planned for replacement to bring production and backup storage in-house and avoid an estimated $230,000 annual licensing charge.
"We can do what we're gonna do we're gonna do anyways next year, this year with no new money spent this year, just pulling out fixed assets that we were gonna spend next year anyways and have a cost avoidance of 230,000," Bridal Austin said, outlining the approach to accelerate purchases and use reappropriated assets. IT staff and the director explained the change was prompted after Microsoft eliminated a licensing option used in the Google environment, and Google offered a compliance pathway priced at about $230,000 a year.
Staff also flagged ongoing Google subscription costs the county pays monthly. "That contract is about to the term of, 48,000 a month," Philip Sabino (IT) said earlier in the discussion, a figure staff equated to roughly $500,000 a year in total cloud subscription costs. Commissioners asked about timing and risk; staff said vendor lead times for hardware are tight but feasible if orders are placed quickly, and that there is a contingency to ask Google for month‑to‑month coverage if the migration slips.
The board did not take a formal recorded vote. Instead, after discussion the chair asked for a show of support and recorded five commissioners offering an informal "thumbs up" to move forward to the Q2 budget review process, where staff will seek formal appropriation and reconfiguration of the identified fixed assets.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.