Board awards $1.11 million drainage improvement contract to Clark Construction

River Ridge Community Development District Board of Supervisors · April 28, 2026

Summary

After reviewing MRI and Clark bids, the Board approved The Clark Construction Group, Inc. bid for four stormwater management phases with an added 5% contingency, for a not-to-exceed amount of $1,111,860.

District staff and the District Engineer presented multiple bids for four stormwater management phases covering Oak Run, Turnberry, Palmetto Dunes and Seaside IV. The Board added an additional 5% contingency to cover unknowns — on top of a contractor-included 15% — which increased the Grand Total from $1,058,914.45 to $1,111,860.

Mr. Krebs explained contingency funds will cover unit-cost items such as tree removal, replanting and capping existing golf-course drains. The Board approved The Clark Construction Group, Inc. bid, with the additional 5% contingency, on a motion by Mr. Blumenthal and a second by Mr. Mountford; the motion carried unanimously.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source