Council authorizes change order and engineering amendment for wastewater treatment project

Preston City Council · March 6, 2025

Summary

Keller Associates presented change order number 1 and engineering amendment number 3 for the wastewater treatment plant; council approved the change order (just over $200,000 variance tied to control panels, soil/backfill and other items) and an engineering pass-through purchase for SCADA equipment.

Keller Associates presented the council with change order number 1 for the wastewater treatment plant contractor and an associated engineering amendment. The firm said the change order includes control panel work and soil/backfill adjustments related to the filter building; the net change described was just over $200,000 and the project remains ahead of schedule and under contingency.

Council approved change order number 1 and later approved engineering amendment number 3 to allow direct procurement of SCADA hardware and software (a pass-through item required by USDA procurement rules). The consultant noted the project is approximately 60–70% complete and that remaining long‑lead items have been managed to keep schedule recovery on track.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source