Council awards Ridge Road Phase 2 bid to JMC for $474,405; engineer details multiple stormwater projects
Summary
Engineer Radisson updated council on two north-end stormwater projects and recommended awarding a grant-funded contract to JMC Contractors; later council approved the Ridge Road Phase 2 bid award to JMC for $474,405, with stormwater impoundment as the primary project goal and an add-alternate for a community garden.
Get email alerts on the Stormwater Infrastructure topic
No spam. Unsubscribe anytime.
Engineer Radisson told council the borough has two stormwater projects on the north end of town that include rain gardens, bump-outs and additional piping; one project is waiting final paperwork before going out to bid. Radisson said staff had posted a second project for bidding in March, was pleased with the bid results, and recommended awarding the funded contract to JMC Contractors, who have worked in the borough and Delaware County.
Later in the meeting Council member Jen Malcoon moved to approve the bid award for Ridge Road Phase 2 to JMC in the amount of $474,405. The motion passed unanimously. Radisson said the primary goal is stormwater impoundment and infiltration, and that an add-alternate includes a decorative series of rain gardens, a picnic table and a small shed; six parking spaces and an HOP permit for the Robynous Road connection were noted as part of implementation details.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.