District secures SFWMD drainage approval; gatehouse renovations move to pre-construction

River Ridge Community Development District Board of Supervisors · May 26, 2026

Summary

The River Ridge CDD reported May 26 that South Florida Water Management District approved drainage repairs and a virtual pre-construction meeting with SFWMD and the Village of Estero is scheduled for June 1, 2026; staff said work will begin once the contract is executed.

District staff and the engineer told the Board that the submittal package for the Pelican Sound gatehouse renovations is ready for submission to the Village of Estero once checks are issued by Bowman Incorporated, and that SFWMD approval for the drainage repairs has been received.

Charlie Krebs and Eric Long said a virtual pre-construction meeting with SFWMD and Village officials is scheduled for June 1, 2026. Mr. Long told the Board that after the pre-construction meeting the contract would be executed and "the work will commence in June." Staff discussed phasing, potential change orders, conduit and transformer work and water-quality testing. The Board signaled readiness to proceed once administrative steps were complete.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source