Evergreen Elementary project reported ahead of schedule; GMP 3 to be presented next meeting
Summary
District presenters said Evergreen Elementary construction is progressing "extraordinarily well," with footings poured, utilities and sidewalks in place, and GMP 3 — the guaranteed maximum price covering the full project — to be presented at the next board meeting.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
A district construction presenter provided an upbeat update on Evergreen Elementary, saying site work is complete and crews have poured footings and installed utilities and sidewalks. "The project is moving along extraordinarily well," the presenter said, noting prefabrication of walls and plans to start floor pours as early as next week.
The presenter said the team has executed three contract amendments and two GMPs, and that GMP 3, which will encompass the full project budget under progressive design‑build, will be presented at the next board meeting. He explained OSPI requires documentation of a constructability review and a value‑engineering report even under the progressive design‑build delivery. The board and superintendent discussed schedule risk, a tight occupancy target in late July, and monitoring strategies; the superintendent noted the district is "pushing on risk" and planning move‑ins so the facility "pops" for students and families.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.