Greendale schedules pump tests, 6–7 month design for water-plant renovations

City of Greendale Board of Public Works · September 10, 2026

Summary

Consultant American StructurePoint will finalize a basis-of-design by month-end to update cost estimates for the water-plant renovation; staff expects detailed design to take 6–7 months and plans to issue an RFQ at 30% design to secure pricing.

City staff reported that American StructurePoint will finalize the water-plant basis-of-design by the end of the month, which will provide an updated cost estimate and clear the way for a 6–7 month detailed design phase. The Chair said the consultant's work will allow the city to move toward a procurement strategy modeled on earlier sewage-plant work: "at 30% plans ... put down an RFQ for the project" to lock in a contractor price.

Board members discussed contracting approaches, including guaranteed-max-price and construction-manager-at-risk models, and said staff will present design materials in advance of future meetings to allow questions. The Chair noted pump tests (the high-service pumps) will be scheduled with staff participation and that the consultant will present the basis-of-design once it is complete.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source