Council notes $252,801.58 Chub Run payment and engineering progress on AMD phases

Town of Nutter Fort Council · May 26, 2026

Summary

Treasurer reported the Sanitary Board approved Chub Run Requisition #13 for $252,801.58; engineering staff said Phase I of the AMD project is complete and Phase II has 31 of 33 ROWs in hand with a DOH permit under review.

Treasurer Leslie Cummings told council that the Sanitary Board met and Chub Run Requisition #13 was approved for $252,801.58, a payment item the town will record as part of Sanitary Board project disbursements.

Engineering staff reported on AMD project sequencing: Phase I is complete; Phase II shows 31 of 33 required right-of-way (ROW) acquisitions in hand and a reroute of the original route has been made while the Department of Highways permit is under review. The Chub Run item was discussed again as engineering noted a successful vendor bid opening and future phase planning.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source