Citizen Portal

Engineers say drainage sized for 100-year event; commission discusses height cap and code allowances

Goddard Planning Commission · March 9, 2026

Summary

MKC Engineering told the planning commission that storm sewer pipes are sized to handle a 100-year event for the bulk of the site, commissioners discussed interior ceiling heights and the International Building Code allowance for sprinklered buildings, and staff proposed considering a zoning-height update in April.

During the site plan review for Reserves at Meadows 25, the project's engineering representative described stormwater design and grading measures, and commissioners discussed how building-code allowances may differ from local zoning height limits.

An MKC Engineering representative explained that "the storm has been sized to take the 100-year event" for roughly 80% of the site and described inlet and overflow elevations along the roadway and the detention pond scheme to accept runoff. The engineer also noted sidewalk grades would require a meandering sidewalk to meet accessibility requirements (slopes under 5%).

Separately, commissioners and staff discussed the project's height issue. Staff reported the design height of 66 feet 10 inches exceeds the general business district maximum of 62.5 feet; an architect (referenced in the meeting) suggested that, because the building will be sprinklered, the International Building Code could allow taller buildings (participants said the IBC could allow up to 70 feet for sprinklered buildings). One commissioner proposed the city consider amending zoning to better reflect code allowances later in April.

The commission's conditional approval of the site plan allows engineering plan review and administrative permitting to proceed while those code and variance issues are resolved at the upcoming variance hearing.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source