RHS Building Committee Meeting 12/3/25
Revere City project committee · December 4, 2025
Revere City project team reported that the 90% construction documents are ready for submission to the MSBA, but soil conditions have created a schedule delay that likely pushes move-in past the planned August/September 2028 date to after the New Year. The committee voted to submit the 90% package to MSBA and approved two accounting housekeeping budget revision requests (BRR 11 and BRR 12).