Citizen Portal
Sign In

2026 - City Council Retreat - Nature Center Design Process

Lewisville City Council / Parks Department presentation · March 5, 2026

City parks staff presented design concepts and recommended GFF MSR as the design partner for a proposed nature center at Lewisville Lake Environmental Learning Area (LELA); staff estimated an all-in project cost of $11–$13 million, a roughly 20,000-square-foot program, and a target to bring contract terms to council on April 2 with a potential groundbreaking in late 2027–early 2028.

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.