2026 - City Council Retreat - Nature Center Design Process
Lewisville City Council / Parks Department presentation · March 5, 2026
City parks staff presented design concepts and recommended GFF MSR as the design partner for a proposed nature center at Lewisville Lake Environmental Learning Area (LELA); staff estimated an all-in project cost of $11–$13 million, a roughly 20,000-square-foot program, and a target to bring contract terms to council on April 2 with a potential groundbreaking in late 2027–early 2028.