3/18/26 - School Building Committee
Central Falls School Building Committee · March 18, 2026
The Central Falls School Building Committee received a construction update for the new high school, including a temporary certificate of occupancy and a 2,500-item punch list with a 60-day window to close open items. The committee paused votes on the demolition/abatement contract and the 60% construction-document submission after demolition bids came in over the project budget and approved four invoice reimbursements as bundled payments.
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.