2026-04-27 Lawrenceburg Utility Service Board Meeting
USB work session (Lawrenceburg City) · April 28, 2026
Consultants presented a 58-page electric load growth study recommending a new substation near U.S. 50/IN-48 and upgrades to Aurora Road and North circuits within 3–10 years to avoid transformer overloads and loss of redundancy; no binding votes were taken due to lack of quorum.
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.