The Pine Board of Adjustment on May 5, 2026 approved a conditional-use permit and a variance for Giga Project 19 Madison LLC to build a 10‑megawatt, air‑cooled modular data facility on city‑leased land, imposing conditions including berming, acoustic fencing, periodic third‑party sound testing and landscaping after public concerns about noise, site stability, drainage and visual impacts.