Fire Station 3 Building Committee - January 22, 2026

Fire Station 3 Building Committee · January 22, 2026

The Fire Station 3 Building Committee met and heard an architect update on construction progress and schedule, approved Change Order 6 and a payment-processing motion, and accepted construction-manager reports. Members discussed a proposed catch-basin fix and remaining contingency funds ahead of a planned occupancy date.