North St. Paul City Council Workshop - 6/02/26

North St. Paul City Council · June 3, 2026

The North St. Paul City Council met to receive an engineering update on a proposed new water tower at Tower Park. Staff and the consultant outlined a recommended 750,000-gallon composite tower, a likely 2027 design/2028 construction timeline (with possible pre‑work in 2026), funding from a $4.5 million state grant, and community/utility coordination needs.