Ad-Hoc Facilities Committee- June 9th 2026

School Building HVAC Project Committee · June 9, 2026

The School Building HVAC Project Committee met June 9, 2026, and received a progress update on electrical, VRF classroom cooling, gym and auditorium work; members approved a $11,976 credit to change to bolted steel connections and approved four invoices, including a $1.416M requisition for Gilbane. The committee set the next meeting for July 7, 2026.