TASD Building & Ground Committee Meeting 6/18/2026

Tunkhannock Area SD Facilities Committee · June 18, 2026

Committee members of Tunkhannock Area SD recommended the district not proceed with a proposed ~5 MW solar array after a utility-provided estimate for required grid upgrades rose sharply to about $1.05 million (±50%), undercutting near-term savings projections; the committee will forward the recommendation to the full board for a vote.