The Town of Greenwich Department of Public Works and consultant WMC presented plans to replace the Fairfield Road culvert over East Branch Brothers Brook with a precast four‑sided box culvert using accelerated bridge construction; construction is planned to begin in spring 2027 with a partial full road closure in summer 2027 and final restoration in fall 2027.